Planning law question:
I have carried out building works without planning permission. What is the time limit for the council to take action against me?
Responses:
Good Lawyer Guide's response
The general rule is four years. This covers building works (eg putting up an unauthorised extentsion or roof-conversion), or changing a non-residential building into a house. In all other instances (eg changing a house into an office) there is a ten-year period.
Do you have a response to add to this question? Login to post a response.